Karuma Bridge Closure: Second Phase Begins

 

The second phase of the Karuma Bridge closure starts today, with work expected to be completed in two weeks. The Ministry of Works and Transport had initially begun this maintenance. Previously only small trucks have been able to use the bridge.

Expansion Joint Installation

Over the next two weeks, the Ministry will be installing expansion joints to enhance the bridge’s durability and safety. This marks a critical phase in ensuring the long-term functionality of one of Uganda’s key transport routes.

Alternative Routes Provided

In an exclusive interview with Salt Media, the Minister for Works and Transport, General Katumba Wamala, outlined alternative routes for travelers:

  1. Western Route: Luweero - Kafu - Masindi - Paraa, through Murchison Falls National Park to Pakwach.
  2. Eastern Route: Nakalama - Tirinnyi - Pallisa - Kumi - Soroti - Lira to Gulu.
  3. Additional Routes: Soroti - Rwenkunyu, Masindi - Apac - Lira.

Motorists are advised to plan accordingly and use the recommended routes to minimize travel disruptions.

Stay tuned for more updates on the Karuma Bridge renovations.

Send us feedback

Salt Media

Latest Posts